TABLE OF CONTENTS
2. SUMMARY
OF EM&A REQUIREMENTS AND MONITORING RESULTS
6. ENVIRONMENTAL
COMPLAINT AND NON-COMPLIANCE
7. IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURES
FIGURES
Figure 1 Project General Layout
Figure 2 Air
and Noise Monitoring Locations
LIST OF APPENDICES
Construction
Programme |
|
Project Organization Chart |
|
Action
and Limit Levels for Air Quality and Noise |
|
Graphical
Presentation of Monitoring Data |
|
Waste Flow Table |
|
Environmental
Mitigation Implementation Schedule (EMIS) |
|
|
|
|
|
i. The Civil
Engineering and Development Department HKSAR has appointed MateriaLab
Consultants Limited (MCL) to undertake the Environmental Team services for the
Project and implement the EM&A works.
ii. This is the twentieth
Quarterly EM&A Report presents the environmental monitoring and audit works
for the period between 1 December 2020 and 18 March 2021. As informed by the
Contractor, major activities in the reporting period included:
December
2020 |
January
2021 |
February
2021 |
March 2021 |
· Landscape works –
irrigation systems, tree and shrub planting |
·
Landscape works – irrigation systems, tree and shrub planting |
·
No Major construction activities |
·
No Major construction activities |
Breaches of the Action and Limit Levels
iii.
Seven Action Level exceedance for 24-hr TSP were recorded in the
reporting period. Two exceedance were recorded at KER1 on 23 December 2020 and
20 January 2021. Five exceedance were recorded at KTD2c on 4, 14, 20 and 26 January
2021 and 1 February 2021.
iv. A Limit Level exceedance for 24-hr TSP was
recorded in the reporting period. An exceedance was recorded at KTD2c on 29
December 2020.
v.
A Limit Level exceedance for construction noise was recorded. Exceedance
was recorded at KER1 on 30 December 2020. No Action / Limit Level exceedance
was recorded for construction noise at KTD1 and KTD2c in the reporting month.
Complaint, Notification of Summons and
Successful Prosecution
vi. No environmental complaint and no
notification of summons and successful prosecution were received in the
reporting period.
Reporting Changes
vii.
The proposal for Termination of EM&A Programme under this Contract
was certified by the ET Leader, verified by the IEC on 15 December 2020,
approved by EPD on 18 March 2021. The construction phase of EM&A Programme
has been terminated on 18 March 2021.